The 2024 Storm Water Drainage Project in Russells Point conducted in conjunction with the Army Corp of Engineers is scheduled to begin Wednesday, April 24, weather permitting.
There are various areas around the Village of Russells Point that will be affected by this important project.
The project should be substantially completed by Oct. 1. Site and design plans are available at the Russells Point Municipal Building for review during regular office hours.
The follow areas will be started Wednesday, April 24:
• Lincoln Boulevard from Point Place Apartments to behind Indian Lake Villa; and
• Garfield Avenue, Madison Avenue, to Madison Street ending at State Route 708.
Traffic will be maintained during construction. Motorists should use caution when traveling in these areas.
If you experience any issues during this storm water drainage project, contact Justin Rice of Helms and Sons Excavating at (419) 422-7738 ext. 104 or jrice.
“We appreciate patience and cooperation from the public during this project,” Russells Point officials said.